Website Rebuild Project - Server & Infrastructure
✅ All Development Phases Successfully Completed
15 Days Complete - Tuesday, 17th June 2025
🚀 Backend Development Complete!
🎯 Target achieved: 100% of planned code delivered
Wed, 28 May 2025 | 185 lines | ⭐⭐ Complexity
✅ Working development environment, basic project structure
Thu, 29 May 2025 | 780 lines | ⭐⭐⭐⭐ Complexity
✅ Core UI components, responsive layouts, animation framework
Fri, 30 May 2025 | 595 lines | ⭐⭐⭐⭐ Complexity
✅ Full Sanity CMS integration, content schemas, Studio deployment
Mon, 2 Jun 2025 | 385 lines | ⭐⭐⭐ Complexity
✅ Complete S3 integration, file upload system, asset management
Tue, 3 Jun 2025 | 705 lines | ⭐⭐⭐⭐ Complexity
✅ Complete page structure, SEO optimization, responsive navigation
Wed, 4 Jun 2025 | 285 lines | ⭐⭐⭐ Complexity
✅ HubSpot API integration, visitor tracking, basic contact creation
Thu, 5 Jun 2025 | 875 lines | ⭐⭐⭐⭐⭐ Complexity
✅ Complete CRM automation, lead scoring, sales notifications
Fri, 6 Jun 2025 | 580 lines | ⭐⭐⭐⭐ Complexity
✅ Production-ready form system, validation, spam protection
Mon, 9 Jun 2025 | 485 lines | ⭐⭐⭐⭐ Complexity
✅ Complete API infrastructure, security measures, documentation
Tue, 10 Jun 2025 | 230 lines | ⭐⭐ Complexity
✅ Complete analytics setup, monitoring dashboard, backup systems
Wed, 11 Jun 2025 | 295 lines | ⭐⭐⭐ Complexity
✅ Performance optimized site, 95+ Lighthouse score achieved
Thu, 12 Jun 2025 | 385 lines | ⭐⭐⭐ Complexity
✅ Production-ready security implementation
Fri, 13 Jun 2025 | 95 lines | ⭐⭐ Complexity
✅ Fully tested and debugged system
Mon, 16 Jun 2025 | 125 lines | ⭐ Complexity
✅ Complete documentation suite, developer guides
Tue, 17 Jun 2025 | 50 lines | ⭐ Complexity
✅ Production deployment, live website, handoff documentation
15-Day Development Plan Successfully Executed
🚀 Ready for production deployment and client handoff
All deliverables completed on schedule
Days Complete
Days Remaining
Backend Lines Written